Potomac Avenue and Glebe Road Complete Streets

Page updated on October 18, 2023 at 10:48 AM

Transportation Planning

  • Alexandria Mobility Plan
  • Alexandria Transit Vision Plan
  • Bicycle Parking
  • Bus Rapid Transit Network
  • Complete Streets
  • Dockless Mobility
  • Traffic & Parking Board
  • T&ES

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Background

The Potomac Yard Metrorail Station is anticipated to open in Alexandria in the fall of 2022. The south station entrance will open onto the Potomac Yard Trail at Potomac Avenue and glebe Road. Once the station opens, potential conflicts are anticipated given the increased volume of people walking, biking, riding the bus, and driving to access the new station. The goal of this project is to enhance pedestrian, bicycle, and transit access and minimize conflicts between people traveling in this area.

Existing Conditions

Potomac Avenue looking north to Glebe Road. The Potomac Yard Metrorail Station will be to the right of the trail (east). The National Industries for the Blind and the American Physical Therapy Association are located on the left (west).

Potomac Ave at Glebe Road Facing North

Project Timeline

Community Engagement: Ongoing
Design: Fall 2021-Summer 2022
Construction: Summer 2023

Project Development

Community Engagement

Status: Ongoing

Staff has engaged directly with stakeholders to gather input and feedback on potential intersection improvements, including the National Industries for the Blind, The Potomac Yard Metrorail Implementation Group (PYMIG), Alexandria Families for Safe Streets, and the Alexandria Bicycle and Pedestrian Advisory Committee.

February 2022 | PYMIG Update
October 2021 | PYMIG Update

Traffic & Parking Board Approval

At its June 27 Public Hearing, the City's Traffic & Parking Board voted unanimously to approve the conversion of the existing eastbound right-turn lane to a bus-only lane.

June 27 Traffic & Parking Board Meeting Materials:
Docket (Item #5)
Presentation
Meeting Minutes

Design

Status: Complete

Concept Plan Overview
30% Design
​​​​​​​60% Design
Final Design Plans

Construction

Status: In Progress

The intersection improvements were completed in early Summer 2023, including the bus-only lane, new curb ramps, median refuge, new crosswalks, No Turn on Red restrictions, and signal timing changes. Improvements on the trail adjacent to the Metro entrance were delayed due to lead times for materials. The project is expected to be complete in Fall 2023.

Contact

For more information on this project, contact Alex Carroll, Project Manager, at Alexandria.Carroll@AlexandriaVA.gov. 

Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...