Hooff's Run Culvert Maintenance Work

The Street and Sewer Maintenance Division will begin culvert maintenance work at the Hooff’s Run Culvert from East Linden Street to the Duke Street.
Work is scheduled to start on December 2, 2024, and expected to continue until April 30, 2025.
- Work hours: Monday-Friday: 7:00 a.m.-6:00 p.m., weather permitting; No weekends or Holidays
- Phase I: Barrel 1- Cleaning and Maintenance: December 2024 through January 2025
- Phase II: Barrel 2- Cleaning and Maintenance: February 2025 through June 2025
- All work is below ground level
- Please adhere to No Parking signs
- Staging areas located in Linden Street Alley, Mt Vernon Avenue cul-de-sac and Hooff’s Run Park and Greenway
For additional questions or concerns, please contact: lisa.jaatinen@alexandriava.gov or alexandriava.gov/Alex311
Arlington Ridge Road/Mount Vernon Avenue Bridge Reconstruction Project
Arlington County and the City of Alexandria are working as partners on the Arlington Ridge Road/Mount Vernon Avenue Bridge Reconstruction Project.
The project will replace the deteriorated roadway and underlying bridge deck of the bridge between Arlington County and the City of Alexandria. The project will return the bridge to a safe operational condition for all users and improve access for pedestrians and bicyclists.
Construction will begin in Summer 2025 and is expected to last two years.
The bridge will continue to operate during construction with reduced lane capacity for vehicular traffic. Pedestrians and bicyclists will continue to have access to the bridge through the project construction.
For more information, visit the Arlington County project page.
VDOT Bridge Information
- I-395 Express Lanes project and VDOT closures of the Duke Street/I-395 overpass
- Bridges and Large Culvert Conditions by VDOT District
- State of structures and bridges – VDOT’s annual reports
-
Bridges in VA – General overview