Sanitary Sewer Rehabilitation Project: Del Ray East

The City of Alexandria is rehabilitating sanitary sewer mainlines and manholes in Del Ray East.
Page updated on Oct 1, 2026 at 9:55 AM

Contact

Anup Gautam, PE, PMP, CCM
Technical Project Manger
Department of Project Implementation
703.746.4155

 

Lu Zhang
Civil Engineer IV
Department of Transportation & Environmental Services
703.746.4289

 

MEDIA INQUIRIES

Office of Communications and Community Engagement
newsroom@alexandriava.gov
703.746.3969

 

TRANSLATION SERVICES

Ver esto en español 
ይህንን በአማርኛ ይመልከቱ 
عرض هذا باللغة العربية

If you prefer communication in another language, free interpretation and translation services are available to you, please email 
LanguageAccess@alexandriava.gov or call 703.746.3960.

 

ACCESSIBILITY

For reasonable disability accommodation, contact Anup Gautam at anup.gautam@alexandriava.gov or call 703.746.4155, Virginia Relay 711.

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Phase: 

  • Lateral Rehabilitation - Construction
  • Manhole and Sewer Main Rehabilitation - Completed 2024-2025

Status: 

  • Lateral Rehabilitation: Active
  • Manhole and Sewer Main Rehabilitation: Closed

Location: Del Ray East

Project Description

The City of Alexandria has established an ongoing citywide initiative called the Sanitary Sewer Asset Renewal Program to assess, renew, and improve the performance of the existing sanitary sewer system. Regular inspection and upkeep of this infrastructure is vital for the overall health and proper operation of sewer system infrastructure. It also helps reduce sewer system infiltration and inflow, which is when excess groundwater (infiltration) and stormwater (inflow) enter the sanitary sewer system through structural weaknesses, like cracks and joint failures, and faulty manhole frames. Addressing infiltration and inflow helps reduce the frequency and magnitude of sanitary sewer overflows, and back-ups into homes and businesses.

This project is the first of three phases that will rehabilitate sanitary sewer infrastructure serving portions of Rosemont, Del Ray, North Potomac Yard, Arlandria, and North Ridge. Phase 1 inspections, which focused on sanitary sewer pipes, manholes, and City-owned laterals in the Four Mile Run and Commonwealth Sanitary Sewersheds east of Commonwealth Avenue, were completed in December 2021.

 

Inspection Summary

  • 644 pipes inspected (21 miles of sanitary sewer)
  • 580 manholes inspected
  • 2,611 laterals inspected

 

Inspection Results

  • 150 pipes require rehabilitation (23 percent)
  • 111 manholes require rehabilitation (19 percent)
  • 491 laterals require rehabilitation (19 percent)
Map showing area in northeast Alexandria included in Sanitary Sewer Asset Renewal - E. Del Ray project.
Phase 1 - E. Del Ray Project Area
Map showing manholes located in northeast Alexandria that will be rehabilitated as part of the Sanitary Sewer Asset Renewal - E. Del Ray project.
Manholes that will be rehabilitated during Phase 1
Map showing sanitary sewer pipes located in northeast Alexandria that will be relined as part of the Sanitary Sewer Asset Renewal - E. Del Ray project.
Pipes that will be relined during Phase 1

Funding

Project Budget:

  • Manhole and Sewer Main Rehabilitation (complete): $5,270,000
  • Lateral Renewal: $4,080,000

CIP Section: Sanitary Sewer

Learn more about the City of Alexandria's Fiscal Year Budget.

Learn more about the Sanitary Sewer Asset Renewal Program.

Schedule

Manhole and Sewer Main Rehabilitation

  • Planning: April 2021 - August 2021
  • Design: August 2021 - June 2023
  • Construction: October 2023 - 2025

 

Lateral Rehabilitation

  • Planning: January 2023 - November 2023
  • Design: October 2023 - December 2024
  • Construction: October 2026 - September 2027

Design

Design Update

Lateral Rehabilitation

The design was completed in December 2024 for installation of Top-Hat liners at 62 lateral-mainline connections and installation of T-Liners in 311 laterals from the lateral-mainline connection to the curb line.

View the Design plans and Posters from the open house at the link below:

  • Del Ray East Lateral Design Plans
  • Del Ray East Lateral Posters

Manhole and Sewer Main Rehabilitation

The design was completed in June 2023 for rehabilitation of approximately 34,000 linear feet of sewer mains and 112 manholes.

Construction

Construction Update

Manhole and Sewer Main Rehabilitation

Construction was completed in 2025.

Lateral Rehabilitation

Construction mobilization is anticipated to begin October 2026, and construction is anticipated to be completed within one year.

COMMUNITY MEETING

Pipe and Manhole Rehabilitation

The City held a public meeting at Alexandria City Hall on October 6, 2025 from 7-9 p.m. to discuss the scope of work, schedule, and what to expect during construction.

  • See the meeting presentation

Lateral Rehabilitation

The City will hold a public meeting at Mount Vernon Community School on September 29, 2026 from 6 to 8 p.m. to discuss the scope of work, schedule, and what to expect during construction. 

NOTIFICATION LETTERS

The City of Alexandria and the project contractor(s) will send out two letters on a rolling basis to impacted residents and business owners.

Each letter will be distributed in English and Spanish. 

Timing:

  • First notification: 14 days prior to construction
  • Second notification: 48 hours prior to construction

CONSTRUCTION HOURS

General Construction Activity:

  • Monday-Friday: 7 a.m.-6 p.m.
  • Saturday: 9 a.m.-6 p.m. 

 

Restricted Roadways:

Construction activity on select City arteries, including Commonwealth Ave., Mt. Vernon Ave., E. Glebe Rd., and E. Monroe St., is limited to:

  • Monday-Friday, 9 a.m.-3:30 p.m.
  • Saturday: 9 a.m.-6 p.m. 

 

CONSTRUCTION IMPACTS

Parking

  • No Parking signs to be posted 72 hours in advance
  • Please remove anything in the roadway during the work window during the time indicated on the No Parking signs

 

Water Use

  • Sewers must be dry for proper UV curing
  • Length of suspension varies based on pipe size and length, but typically around six hours

 

Odors

  • Pour small amount of water in any drain taps that might be dry (basement floor drain, for example) to eliminate potential for odors during lining
  • Capital Improvement Program
  • Flooding
  • Infrastructure
  • Public Facilities
  • Sewers
  • Water
Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal
City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...