Sanitary Sewer Relocation at CSX-Fourth Track Project
![Google Translate](https://www4.alexandriava.gov/scripts/d8/c/2/images/icon-GoogleTranslate.png)
Project Summary
Phase: Design
Status: Active
Location: Taylor Run/Duke Street
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City is relocating three segments of the Taylor Run sanitary sewer currently located on CSX property in preparation for CSX's fourth rail project. The sewer segments, which are situated north of the CSX rail tracks and south of Witter Field, include 75 linear feet of 15-inch-diameter and 93 linear feet of 18-inch-diameter pipe. Additional modifications to a manhole will also be required.
The CSX Transportation (CSXT) Expansion project includes the construction of a bridge structure over Taylor Run just north of the existing tracks.
Funding
Project Budget: $500,000
CIP Section: Sanitary Sewers
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: September 2022 - August 2023
- Design: August 2023 - December 2024
- Construction: December 2024 - May 2027
Design
Design Update
A Design Purchase Order (PO) for the preparation of design plans to relocate Taylor Run sanitary sewer mains was issued in January. The City hired a design consultant to develop and analyze potential designs for the sewer reconfiguration. A field coordination meeting with the design consultant and CSX team was held in February. Staff have reviewed the consultant's recommendations and anticipate a 60% design will be submitted by end of May 2024.