Sanitary Sewer Relocation at CSX-Fourth Track Project
Project Summary
Phase: Design
Status: Active
Location: Taylor Run/Duke Street
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City is relocating three segments of the Taylor Run sanitary sewer currently located on CSX property in preparation for CSX's fourth rail project. The sewer segments, which are situated north of the CSX rail tracks and south of Witter Field, include 75 linear feet of 15-inch-diameter and 93 linear feet of 18-inch-diameter pipe. Additional modifications to a manhole will also be required.
The CSX Transportation (CSXT) Expansion project includes the construction of a bridge structure over Taylor Run just north of the existing tracks.
Funding
Project Budget: $500,000
CIP Section: Sanitary Sewers
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: September 2022 - August 2023
- Design: August 2023 - December 2024
- Construction: December 2024 - May 2027
Design
Design Update
The design Purchase Order (PO) was issued in January 2024 to prepare design plans to relocate the Taylor Run sanitary sewer mains. The field coordination meeting with the design consultant and the CSX team was held in February. The design contractor had submitted an alternatives design development report (ADDR) report, which presents the alignment alternatives evaluation and findings, and the conceptual design of the Taylor Run sanitary sewer relocation on CSX property. The 90% design will be submitted by the end of Summer 2024.