Madison Street and North Saint Asaph Street Sewer Replacement

Capacity and drainage improvements are being made to the sewer system at the intersection of Madison Street and North Saint Asaph Street.
Page updated on Jan 23, 2026 at 2:05 PM

Contact

Anup Gautam, PE, PMP, CCM
Technical Project Manager
Department of Project Implementation
703.746.4155

Dung Huynh
Civil Engineer III
Department of Transportation & Environmental Services
703-746-4052

 

MEDIA INQUIRIES

Office of Communications and Community Engagement
newsroom@alexandriava.gov
703.746.3969

 

TRANSLATION SERVICES

Ver esto en español 
ይህንን በአማርኛ ይመልከቱ 
عرض هذا باللغة العربية

If you prefer communication in another language, free interpretation and translation services are available to you, please email 
LanguageAccess@alexandriava.gov or call 703.746.3960."

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Phase: Construction

Status: Active

Small Area: Old Town North

Sponsor Dept.: Transportation & Environmental Services

Map of Alexandria with a red box indicating the project location of Madison Street and North Saint Asaph Street.
View in Google Maps

Project Description

The City of Alexandria is pursuing a combined sewer repair project to address sewer back-ups following wet weather events.
 
The project will include:

  • Increasing the size of existing sewer pipes in the intersection of Madison Street and North Saint Asaph Street to provide additional system capacity,  
  • Installing new curb inlets to improve drainage, and  
  • Relocating existing the sewer line on Madison Street to provide better drainage.  

Funding

Project Budget: $500,000

CIP Section: Sanitary Sewers

Learn more about the City of Alexandria's Fiscal Year Budget.

Schedule

  • Planning: September 2021 - September 2022
  • Design: September 2022 - August 2024
  • Construction: September 2024 - April 2026
    • Construction Site Activity: January - March 2026 

Construction

Construction Update

Construction is beginning at the intersection of Madison St. and N. St. Asaph St. and is scheduled for completion in late March 2026.

Test pit drilling is underway and the excavation area has been marked. Excavation of the roadway is scheduled to begin the final week of January; however, this may be delayed until early February due to the major winter storm forecasted for Sunday, January 25. 

 

Construction Hours:

  • Monday through Friday: 9 a.m. to 3:30 p.m.
  • Saturday: By special request only
  • Sunday: No construction activity

 

Roadway Closures:

  • South Lane of Madison St.
  • West Lane of N. Asaph St.
  • The roadway will reopen to traffic outside of work hours. 

 

Sidewalk Closures:

  • Southwest corner will be closed.
  • Crosswalk will be closed during excavation.
  • Royal Restaurant will be accessible at all times.
     

Parking Restrictions:

  • No Parking signs have been posted. Please follow all official signs as marked. 

 

Detours/Maintenance of Traffic:

  • Flaggers will be on site to direct traffic and detour signs will posted to provide crossing alternatives. 

 

Current Project Site Photos

Photo of test pit and excavation markings in the intersection at Madison St. and N. St. Asaph St.
Photo of test pit, excavation, and project extent markings on N. St. Asaph St.
of
Grid View Close Modal
Photo of test pit and excavation markings in the intersection at Madison St. and N. St. Asaph St.
Test pit and excavation markings are now visible in the intersection at Madison St. and N. St. Asaph St.
Photo of test pit, excavation, and project extent markings on N. St. Asaph St.
Test pit, excavation, and project extent markings are visible on N. St. Asaph St. between Harris Teeter and Royal Restaurant.

CONSTRUCTION Outreach

City contractor, Sagres Construction, will be installing new sanitary sewer pipe, new manholes, and capping a portion of the existing sanitary line at the intersection of Madison Street and North Saint Asaph Street starting in late 2025. 

Pre-Construction Community Meeting:

The City held a pre-construction community meeting, featuring a presentation on project construction followed by a question-and-answer session. 

  • Date: Monday, July 14, 2025
  • Time: 6:30 – 7:30 p.m.
  • Location(s): City Hall, Sister Cities Conference Room (301 King Street) and Zoom
  • Description: Staff will provide project details such as the project schedule, work hours, what to expect during construction, and how construction-related impacts will be managed.
  • Meeting Presentation
  • Meeting Video
  • Capital Improvement Program
  • Flooding
  • Infrastructure
  • Sewers
  • Stormwater
  • Water
Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...