Landmark Mall I-395 Ramp Improvements
Project Summary
Phase: Design
Status: Active
Location: Landmark/Van Dorn
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City of Alexandria is updating the exit ramp leading from northbound I-395 to eastbound Duke Street. The ramp and roadway interchange improvements are necessary to facilitate direct emergency vehicle access to the new INOVA Hospital complex planned for the former Landmark Mall site. Additionally, vehicular traffic is anticipated to increase associated with the new development.
Funding
Project Budget: $11,630,000
CIP Section: Transportation
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: January 2022 - December 2022
- Design: August 2022 - June 2025
- Construction: February 2025 - January 2028
Design
Design UPDATE
This project is currently awaiting approval from VDOT for the Operational and Safety Analysis Report (OSAR). VDOT provided initial comments for the City's draft submission in November, 2022. Staff responded to VDOT's comments and resubmitted the proposed design concept for VDOT's final review and approval of the OSAR on April 4 and June 13. In parallel, the City's design consultant began addressing 30% design review comments provided by the City and VDOT. Staff continues to actively communicate / coordinate with VDOT and the adjacent developer to foster project advancement in order to achieve all project milestone dates.