Project Summary
Phase: Planning
Status: Active
Location: Arlandria-Chirilagua
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City of Alexandria will rehabilitate five existing Four Mile Run outfalls and install new gabion baskets in conjunction with the Four Mile Run Federal Flood Control Project.
This project is anticipated to begin in July 2025. Additional information will be posted as the project progresses.
Funding
Project Budget: $500,000
CIP Section: Stormwater Management
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: July 2025 - July 2026
- Design: July 2026 - July 2027
- Construction: July 2027 - July 2028
Planning
This project is scheduled to start planning in FY 2026. There is currently no active work taking place on this project.
Learn more about Four Mile Run:
- Four Mile Run Dredge Project (In Partnership with Arlington County)
- History of Four Mile Run
- Four Mile Run Master Plan