East Mason Avenue and East Duncan Avenue Stormdrain Connection
Project Summary
Phase: Planning
Status: Active
Location: Potomac West
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The E. Mason Avenue and E. Duncan Avenue Stormdrain Connection project aims to reduce the frequency and magnitude of flooding on the 300 block of E. Mason Avenue. The City of Alexandria determined that increasing the size and capacity of the storm sewer pipe running from E. Mason Avenue to E. Duncan Avenue parallel to Dewitt Avenue is the best feasible solution for this location.
Funding
Project Budget: $560,000
CIP Section: Stormwater Management
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
Note: Work on this project has not yet started. The following schedule is preliminary and subject to change.
- Planning: July 2025 - July 2026
- Design: July 2026 - July 2027
- Construction: July 2027 - July 2028
Planning
Planning Update
This project is scheduled to start planning in FY 2026. There is currently no active work taking place at this time.
SPONSOR Program
This project is part of the Flood Action Alexandria program. In response to more frequent, intense climate-change-induced storm events, the City of Alexandria launched Flood Action Alexandria, a multipronged program to help address flooding issues in our community.