East Glebe Road and Route 1 Intersection Improvements Project
The City is planning improvements for the intersection of East Glebe Road and Route 1.
Page updated on Jul 19, 2024 at 5:18 PM
XWARNING: You have chosen to translate this page using an automated translation system.
This translation has not been reviewed by the City of Alexandria and may contain errors.
Project Summary
Phase: Planning
Status: Active
Location: Potomac Yard/Potomac Greens
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The East Glebe Road and Route 1 intersection improvement project consist of constructing an exclusive left-turn lane, through lane, and right-turn lane in the eastbound direction, and enhancements to assist safe vulnerable user crossing.
Funding
Project Budget: $3,460,000
CIP Section: Transportation
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: July 2024 - December 2025
- Design: January 2026 - February 2028
- Construction: March 2028 - August 2030
Planning
Planning Update
Project details and updates will be provided as the Planning phase progresses. Work on the Planning phase is anticipated to begin in July 2024. Staff will coordinate with VDOT to obtain all necessary approvals to advance the project.