Bridge Repair: Van Dorn Over Holmes Run Project

The City performed preventive and restorative maintenance to the Van Dorn Street Bridge over Holmes Run in the Landmark area of Alexandria.
Page updated on Jul 15, 2024 at 7:30 AM

Contact

Ayoub Hassen, PE, PMP
Technical Project Manager
Department of Project Implementation 
703.746.4635

 

Lisa Jaatinen
Civil Engineer IV, Special Projects
Department of Transportation & Environmental Services
703.746.4053

 

MEDIA INQUIRIES

Office of Communications and Community Engagement
newsroom@alexandriava.gov
703.746.3969

 

TRANSLATION SERVICES

Ver esto en español
ይህንን በአማርኛ ይመልከቱ 
عرض هذا باللغة العربية

If you prefer communication in another language, free interpretation and translation services are available to you, please email LanguageAccess@alexandriava.gov or call 703.746.3960.

 

Accessibility

For reasonable disability accommodation, contact Ayoub Hassen at ayoub.hassen@alexandriava.gov or call 703.746.4635, Virginia Relay 711.

Share

Share on Twitter Share on Facebook
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Project Summary

Phase: Construction

Status: Substantially Complete

Location: Seminary Hill/Strawberry Hill

Managing Dept.: Project Implementation

Sponsor Dept.: Transportation & Environmental Services

Project Description

The City of Alexandria repaired the Holmes Run culvert at Van Dorn St. Each year, Federal officials conduct bridge inspections throughout the city as part of the Bridge Inspection Program, in an effort to extend the life of bridges by maintaining their condition. Following the completion of the 2020 inspection, the City established a long-term maintenance plan and identified a series of immediate repairs required to extend the life of this culvert. The solution for this bridge included preventive and restorative maintenance such as repairs to the metal pipe, and concrete bridge walls and slabs.

Van Dorn Culvert Over Holmes Run

Photo of Van Dorn Bridge over Holmes Run

Area map of Van Dorn over Holmes Run Bridge Repair Project Location

Area map of Van Dorn over Holmes Run Bridge Repair Project Location

Funding

Project Budget: $2,550,000

CIP Section: Transportation

Learn more about the City of Alexandria's Fiscal Year Budget.

Schedule

  • Planning: June 2020 - September 2020
  • Design: September 2020 - April 2021
  • Construction: July 2022 - July 2024

Planning

Sponsor Program

Bridge Inspections and Maintenance

Transportation throughout the City of Alexandria relies on a network of infrastructure, which includes bridges. As part of this expansive network, the City maintains 29 highway bridges and more than 40 pedestrian bridges. 

Construction

The City of Alexandria contracted Fort Myer Construction to repair the Van Dorn Street culvert over Holmes Run. Work crews installed culvert protection, and repaired the culvert concrete and metal pipe.

General construction activities were permitted to occur Monday through Friday, 7:00 AM to 6:00 PM, and Saturday, 9:00 AM to 6:00 PM.

 

Community Meeting

The City held a public meeting to present the project and answer questions on Thursday, July 20, 2023, from 7 - 8 p.m. at Patrick Henry Recreation Center, Multipurpose Room C, 4653 Taney Avenue, Alexandria, VA, 22304.

 

Construction Impacts

The following temporary impacts to Holmes Run Parkway between North Ripley Street and Van Dorn Street occurred during construction hours: 

  • Closure of the eastbound lane of Holmes Run Parkway
  • Closure of a small segment (no more than 500 feet) of Holmes Run Trail
  • Curbside parking restrictions adjacent to the project site along the eastbound lane

 

Flaggers from the construction crew were present to direct traffic, assist trail users with crossing to the sidewalk on the opposite side of Holmes Run Parkway, and ensure residents have access to their homes.

 

Read the construction notification letter distributed to community members.

  • Capital Improvement Program
  • Infrastructure
  • Public Works
  • Stormwater
  • Streets
  • Transportation
  • Transportation
Contact Us
Alex311 | 703.746.4311
Follow Us
  • Facebook
  • Twitter
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Emergency Hotlines
  • Social Media
  • Privacy & Legal
  • FOIA Requests
  • Departments
  • Jobs
  • Payments

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...