Armistead L. Boothe Park Synthetic Turf Field Conversion
The Field Replacement project will convert the existing natural turf field from a natural grass diamond field with a natural grass overlay rectangular field to a full synthetic turf diamond field with synthetic turf overlay rectangular field. In addition, the project will include upgrades to the field lighting, dugouts, warm up areas, batting cages, spectator seating, scoreboard, and scorers’ table. The project will be ADA compliant and it will address environmental site constraints.
Page updated on Jul 2, 2024 at 11:26 AM
XWARNING: You have chosen to translate this page using an automated translation system.
This translation has not been reviewed by the City of Alexandria and may contain errors.
Location
Armistead L. Boothe Park
520 Cameron Station Boulevard
Alexandria, VA 22304
Status
Final Design
Progress Update
- November 2020, A. Morton Thomas, Inc. was awarded the design contract
- January 2021, on site survey work was completed
- February 2021, A community meeting on the project design was held
- June 2021, Planning Commission approval
Project Schedule
- Design Completion: Summer 2024
- Construction Procurement: Fall/Winter 2024
- Construction Start: Winter 2024/2025
- Substantial Completion: Summer 2025
Public Engagement
- Community Meeting: February 25, 2021 at 7 p.m.
- Virtual Meeting Recording
- Meeting Presentation
- What are we doing? View the Armistead L. Boothe Park Story Map for more information.
- Armistead L. Boothe Survey Results
- Park & Recreation Commission Update - March 18, 2021
- Park & Recreation Commission Public Hearing - April 15, 2021