600 Block of North Columbus Street Sewer Separation Project
Project Summary
Phase: Design
Status: Active
Location: Braddock Road Metro Station
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City is disconnecting the sanitary sewer line for the 600 block of North Columbus Street from the combined sewer and connecting it to a fully separated sanitary sewer line. This will reduce the potential for sewer back-ups into building basements, caused by too much water entering the combined sewer system during periods of significant wet weather.
Funding
Project Budget: $1,000,000
CIP Section: Sanitary Sewers
Learn more about the City of Alexandria's Fiscal Year Budget.
Learn more about the City's Sanitary Sewer infrastructure.
Schedule
- Planning: February 2023 - July 2023
- Design: August 2023 - October 2024
- Construction: October 2024 - April 2027
Design
design Update
The 100% design was submitted by the Consultant. Once the design has been reviewed by the City, the design will be finalized.