300-400 Block North Alfred Street Combined Sewer Upsizing Project
Project Summary
Phase: Construction
Status: Completed
Location: Braddock Road Metro Station
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City of Alexandria enhanced the sanitary and combined sewer system along the 300 and 400 blocks of North Alfred Street to improve performance and increase capacity. This upgrade addressed recurring sewer backups caused by root intrusion—where tree roots enter and obstruct aging pipes—particularly during heavy rainfall.
As part of the project, the City replaced outdated 10" reinforced concrete pipes with approximately 230 linear feet of 18” combined sanitary sewer pipe and 500 linear feet of 15” sanitary sewer pipe. Around 35 property laterals were reconnected to the new main line. The work also included installing three new 48" manholes and one 72" doghouse manhole, while maintaining four existing manholes to support long-term system reliability.
Funding
Project Budget: $780,000
CIP Section: Sanitary Sewers
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: April 2022 - September 2022
- Design: September 2022 - October 2023
Construction: November 2023 - June 2025
Construction
Construction Update
Project construction is complete. City staff have conducted a walkthrough to certify that the repairs were executed as contracted.
Community Events
The City held a pre-construction open house at Alexandria City Hall, Sister Cities Conference Room (First Floor) in-person and virtually on Wednesday, January 22, 2025 at 6:30-7:30pm.
- Meeting Materials: