300-400 Block North Alfred Street Combined Sewer Upsizing Project
Project Summary
Phase: Construction
Status: Active
Location: Braddock Road Metro Station
Managing Dept.: Project Implementation
Sponsor Dept.: Transportation & Environmental Services
Project Description
The City of Alexandria is increasing the storage and performance capacity of both the existing sanitary and combined sewers at four locations along the 300 and 400 blocks of N. Alfred Street. Root intrusion (roots growing into the pipes via cracks) of the sanitary sewer pipe is causing sewer backups in several properties in the 300 and 400 blocks of North Alfred Street during wet weather events.
Funding
Project Budget: $780,000
CIP Section: Sanitary Sewers
Learn more about the City of Alexandria's Fiscal Year Budget.
Schedule
- Planning: April 2022 - September 2022
- Design: September 2022 - October 2023
- Construction: October 2023 - August 2025
Construction
Construction Update
The City is in the process of awarding the construction contract. Active construction is anticipated to begin in Fall 2024.