Potomac Yard Metrorail Station Project Plans and Permits

Page updated on December 11, 2023 at 8:58 AM

Share

Bluesky Share on Facebook Share on X Share via Email
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

The following files contain the approved design elements and plans for the Potomac Yard Metrorail Station:

Board of Architectural Review (BAR) Approvals

The project completed the BAR review process on February 19, 2020:  

  • February 19
    • Glass handrail details
    • Metal louver connection details
    • North Pavilion – stone wall, glazing and lintels 

 

  • January 22

 

  • December 4
    • Lighting
    • Downspout and gutter locations
    • Pedestrian bridge handrail

 

  • October 16
    • North pavilion: footprint, mass, scale, and height  

 

  • September 4
    • Bridge, platform, and mezzanine: mass, scale, and materials sample board 

 

  • July 24
    • Piers, mezzanine, platform roofs: mass and scale 

 

  • July 10
    • Project architectural character, footprint, scale, and height  

Development Special Use Permits

DEVELOPMENT SPECIAL USE PERMIT #2020-10020 (SOUTH PAVILION)

  • Approved DSUP #2020-10020 Staff Report
  • DSUP #2020-10020 Site Plan (Application Use Only/Unsigned)
  • Council Presentation on DSUP #2020-10020

 

DEVELOPMENT SPECIAL USE PERMIT #2018-0017 (STATION AND NORTH PAVILION)

  • Approved DSUP #2018-0017 Staff Report
  • DSUP #2018-0017 Site Plan
  • Council Presentation on DSUP #2018-0017

Environmental Permits

VIRGINIA DEPARTMENT OF ENVIRONMENTAL QUALITY (DEQ) - VIRGINIA WATER PROTECTION PERMIT

The State Water Control Board Meeting took place on Friday, September 6, 2019. The Board unanimously approved the Virginia Water Protection Permit for the Potomac Yard Metrorail Station Project. The Virginia Department of Environmental Quality issued a Virginia Water Protection (VWP) Individual Permit to the City that day.   

Virginia Water Protection (VWP) Individual Permit Number 19-0710

  • Final VWP Individual Permit
  • Fact Sheet

The project's VWP Permit 19-0170 Construction Status Update Forms and Weekly Inspection Checklists are available here.

 

UNITED STATES ARMY CORPS OF ENGINEERS (USACE) - CLEAN WATER ACT (CWA) SECTION 404 PERMIT

The U.S. Army Corps of Engineers (USACE) issued a Clean Water Act (CWA) Section 404 permit to the City of Alexandria for the Potomac Yard Metrorail Station project on November 15, 2019.  

Department of the Army Permit NAO-2012-02012/19-V0170

  • Cover Letter
  • Signed Permit
  • Drawings
  • Certificate of Compliance

Landscape Plans

  • Potomac Greens Park Landscape Plan
  • South Pavilion Landscape Plan

Noise Variances

Sign-up to receive alerts when new construction noise variances are issued. 

The following is a record of the noise variance permits issued for the Potomac Yard Metrorail Station project:

PERMIT: TES2023-00031

Dates: December 1, 2022 - April 30, 2023

Hours: Sunday - Saturday, 12 AM - 11:59 PM

Activity:

  • Installation of Train Control Circuits, Signalization, Trackwork, Building Envelope and Finishes for the new Potomac Yard Metro Station

Materials:

  • This is an extension of permit TES2022-00801. Please the Letter to Residents and Work Area Map below.

 

PErmit: TES2022-00801

Dates: August 1 - November 30

Hours: Monday 6 PM- Sunday 7 AM

Activity: 

  • Installation of Train Control circuits, Signalization, Trackwork, Building Envelope and Finishes for the new Potomac Yard Metro Station.

Materials:

  • ​​​​​​​Letter to Residents
  • Work Area and Access Point Map

 

 

permit: TES2022-00506

Dates: May 15-July 31

Hours: Sunday, 9 AM-6 PM

Activity:

  • Installation of building envelope and finishes at the new Potomac Yard Metro Station site

Materials:

  • Letter to residents

 

Permit: TES2022-00504

Dates: May 16-June 24

Hours: Monday, 6 PM- Saturday, 7 AM

Activity: 

  • Installation of Train Control circuits and signalization within WMATA roadway and new Potomac Yard Metro Station site

Materials:

  • Letter to residents

 

PERMIT: TES2022-00192

Dates: March 12-April 4

Hours: Friday, 6 PM- Monday, 7 AM

Activity:

  • Pedestrian Bridge Concrete Placement

 

Permit: TES2022-00192

Dates: March 18-March28

Hours: Friday, 6 PM- Monday, 7 AM

Activity:

  • Pedestrian Bridge Concrete Placement

Materials:

  • Letter to Residents

 

PERMIT: TES2021-01431

Dates: February 4-March 4

Hours: Friday, 6 PM- Monday, 7 AM

Activities:

  • Excavation, backfill, compaction, ballast placement, and installation of Train Control
    circuits and signalization for the new Potomac Yard Metro Station.

Materials:

  • Letter To Residents

 

PERMIT: TES2021-01105

Dates:  October 22-25

Hours:  Friday, 6 PM- Monday, 7 AM

Activities: 

 

PERMIT: TES2021-01104

Dates:  October 7-31

Hours:  Monday, 5 AM- Friday, 7 AM

Activities: 

 

PERMIT: TES2021-01008

Dates: September 24 - 27

Hours: Friday, 6 PM - Monday, 7 AM

Activities: 

  • Grading, fill placement, compaction, and ballast placement to connect the new station to existing WMATA tracks

Materials: 

  • Letter to Residents

 

PERMIT: TES2021-01005

Dates: September 17 - 20

Hours: Friday, 6 PM - Monday, 7 AM

Activities: 

  • Pedestrian Bridge Conduit and Structural Deck Installation

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00911

Dates: August 27 - 29

Hours: Friday - Monday: 6 PM - 7 AM

Activities:

  • Pedestrian Bridge Conduit and Structural Deck Installation

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00911

Dates: August 27 - 29

Hours: Friday - Monday: 6 PM - 7 AM

Activities:

  • Pedestrian Bridge Conduit and Structural Deck Installation

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00806

Dates: August 1 - 31

Hours: Monday - Friday; 5 AM (start time)

Activities:

  • Installation of Concrete

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00805

Dates: August 6 - 16

Hours: Friday - Monday: 5 AM - 6 PM

Activities:

  • Communications and Signal Upgrades

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00663

Dates: July 6 - 31

Hours: Friday - Monday: 5 AM - 6 PM

Activities:

  • Installation of Concrete

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00662

Dates: July 9 - 25

Hours: Friday - Monday: 6 PM - 5 AM

Activities:

  • Communications and Signal Upgrades

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00537

Dates: June 18 - 21

Hours: Friday - Monday: 6 PM - 7 AM

Activities:

  • Communications and Signal Upgrades

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00332

Dates:

  • June 4 - 7
  • June 11 - 14

Hours: Friday - Monday: 6 PM - 7 AM

Activities:

  • Communications and Signal Upgrades

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00330

Dates: 

  • May 14 - 17
  • May 21 - 24

Hours Permitted:

  • Friday - Monday: 6 PM - 7 AM

Activities:

  • Communications and Signal Upgrades

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00305

Dates: April 30 - May 3

Hours Permitted:

  • Friday - Monday: 6 PM - 7 AM

Activities:

  • Communications and Signal Upgrades

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00263

Dates: April 16 - April 19, 2021

Hours Permitted:

  • Friday - Monday: 6 PM - 7 AM

Activities:

  • Communications and Signal Upgrades

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00250

Dates: March 29 - April 26, 2021

Hours Permitted:

  • Monday - Sunday: 6 PM - 7 AM

Activities: 

  • Pedestrian Bridge Erection

Materials:

  • Letter to Residents

 

PERMIT: TES2021-00136

Dates: February 17 - March 6, 2021

  • Extension: March 7 - 29, 2021

Hours Permitted:

  • Monday - Sunday: 6 PM - 7 AM

Activities: 

  • Pedestrian Bridge Erection

Materials:

  • Letter to Residents
  • Work Area and Access Point Map
  • Letter to Residents (Permit Extension)

 

PERMIT: TES2021-00075

Dates: February 1 - February 16, 2021

Hours Permitted:

  • Monday - Sunday: 6 PM - 7 AM

Activities:

  • Pedestrian Bridge Erection

Materials:

  • Letter to Residents
  • Work Area and Access Point Map

 

PERMIT: TES2020-00899

Dates: September 9 - October 11, 2020

Hours Permitted:

  • Monday - Friday: 5 AM – 7 AM
  • No weekend or holiday work permitted

Activities:

  • Placement and finishing of concrete

Materials:

  • Permit Scope and Conditions
  • Letter to Residents
  • Work Area and Access Point Map

 

PERMIT: TES2020-00652

Dates: July 11 - 31, 2020

Hours Permitted:

  • Monday - Friday: 5 AM – 7 AM
  • Saturday: 5 AM – 9 AM
  • No Sunday or holiday work permitted

Activities:

  • Placement of concrete

Materials:

  • Letter to Residents
  • Work Area and Access Point Map

 

PERMIT: TES2020-00623

Dates: June 25 - July 10, 2020

Hours Permitted:

  • Monday - Friday: 5 AM – 7 AM
  • No weekend or holiday work permitted

Activities:

  • Placement of concrete

Materials:

  • Letter to Residents
  • Work Area and Access Point Map

 

PERMIT: TES2020-00400

Dates: April 26 - May 12, 2020

Hours Permitted:

  • Sunday - Thursday: 9 PM – 6 AM

Activities:

  • Installation of track monitoring equipment

Materials:

  • Permit Scope and Conditions
  • Letter to Residents
  • Work Area and Access Map

 

PERMIT: TES2020-00214

Dates:

  • March 6 - March 8, 2020
  • March 14 - March 15, 2020
  • March 21 - March 22, 2020

Hours Permitted:

  • 9 PM – 7 AM

Activities: 

  • Relocation of WMATA fence
  • Installation of track monitoring equipment

Materials:

  • Letter to Residents
  • Work Area Map

 

PERMIT: TES2019-03348

Other City Permits

PERMIT: TES2021-01012

PERMIT: TES2021-01106

 

  • Capital Improvement Program
  • Permits
  • Plans
  • Public Transportation
  • Transportation
Contact Us
Alex311 | 703.746.4311
Follow Us
  • BlueSky
  • Facebook
  • X
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Jobs
  • Payments
  • Departments
  • Newsroom
  • Social Media
  • Emergency Hotlines
  • Accessibility
  • FOIA Requests
  • Privacy & Legal

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...