FY 25 Budget Q&A #013: In the Proposed CIP, the Tree & Shrub Maintenance project has no funding planned for FY 2025. Please explain this change in funding from the previously approved CIP.

Page updated on December 26, 2024 at 9:40 AM

Quick Access

  • OMB Homepage
  • FY 2025 Budget Questions and Answers

Share

Share on Twitter Share on Facebook
Translate icon
Translate icon
XWARNING: You have chosen to translate this page using an automated translation system. This translation has not been reviewed by the City of Alexandria and may contain errors.

Question: In the Proposed CIP, the Tree & Shrub Maintenance project has no funding planned for FY 2025. Please explain this change in funding from the previously approved CIP. In addition to the Tree & Shrub Maintenance project, what other resources are included in the proposed operating budget and CIP related to planting and maintaining trees in Alexandria? (Mayor Justin Wilson, Councilmember Sarah Bagley, Councilwoman Alyia Gaskins)

Response: 

In the proposed capital improvement program (CIP), the Tree & Shrub Maintenance project’s contemplated FY 2025 budget was reduced from $367,000 in last year’s Approved CIP to zero. The funding for FY 2025 was eliminated in the proposed CIP due to the project having unspent and unencumbered balances from previous capital budget appropriations, totaling over $400,000. This unspent funding, along with encumbered but unspent funds, will be used for tree planting, tree well enlargement, and invasive removal in FY 2024 and FY 2025.

As a strategy to smooth out the significant and increasing costs of the CIP program, accounts with large existing balances that were requesting additional funds in FY 2025 were scrutinized. It was determined, through this review, that the Tree and Shrub account had sufficient funding to finish commitments remaining in FY 2024 along with work to be completed in FY 2025.

Although funding was reduced in FY 2025, the project retains planned funding for FY 2026 through FY 2034, totaling $4,016,000. Along with the Tree & Shrub Maintenance project, the proposed CIP includes investment in urban forestry in the Proactive Maintenance of the Urban Forest project. Proposed FY 2025 funding in this project totals $348,000 and $3,988,000 is contemplated over the 10-year plan. Between these two projects, $8,004,000 of capital funding is proposed to be invested over the 10-year plan.

In addition to the CIP, the proposed operating budget includes support for urban forestry efforts. This includes four staff positions in the Department of Recreation, Parks, and Cultural Activities (Park Services Division); three urban foresters and one urban forest manager. All four of these positions are currently filled.

The table below provides a summary of the last three years of approved operating and capital budgets, along with the proposed FY 2025 budget, for programs related to urban forestry.

FY25 Budget Table 013.1

While the City has invested significant general fund dollars to its urban forestry efforts, the City has also received developer contributions to support this program. The current balance of unspent developer contributions allocated to urban forestry efforts is approximately $77,000.

 

Printable Version

Contact Us
Alex311 | 703.746.4311
Follow Us
  • Facebook
  • Twitter
  • YouTube
Visitor Information

VisitAlexandriaVA.com

  • Emergency Hotlines
  • Social Media
  • Privacy & Legal
  • FOIA Requests
  • Departments
  • Jobs
  • Payments

Alexandria City Hall
301 King Street
Alexandria, VA 22314

City of Alexandria Seal
© 1995–2023 City of Alexandria, VA and others.
Hold on, redirecting...