North Ridge Area Sanitary Sewer Rehabilitation
Project Summary
Current Phase: Planning
Sponsor Project Manager: Alicia Grant, Transportation & Environmental Services
Managing Project Manager: Anup Gautam, Project Implementation
Project Description
The North Ridge Area Sanitary Sewer Rehabilitation Project is a multi-phase capital improvement project with the goal of inspecting the North Ridge area sanitary sewer system, identifying any assets that require monitoring or improvement, and performing targeted repair and rehabilitation projects throughout the project area sewer system.
The North Ridge area is the third phase of the Sanitary Sewer Asset Renewal Program. The goal of the program is to preserve and protect existing City-owned sewer infrastructure, extend its useful life, and protect against pipe collapses and other emergency repairs.
Project Funding
Project Budget
Total Project Budget: $5.1 million
Planning: $1,644,400
Design: $200,000
Construction: $3,255,600
Funding Breakdown
This project is funded using Sanitary Sewer enterprise Fund Revenues and is programmed in the City's Capital Improvement Program.
Project Schedule
Planning: Summer 2023 - Fall 2024
Design: Winter 2024 - Winter 2025
Construction: Spring 2026 - Summer 2027
Planning Phase
Planning Overview
During the planning phase, City staff and engineering consultants conduct a sewer system condition assessment, which requires the inspection of all sanitary sewer mainlines, sewer manholes, and City-owned laterals.
For the North Ridge area, it is expected that 65,600 linear feet of sewers, 323 manholes, and up to 1,400 City-owned laterals will be inspected with CCTV cameras to document the condition of all assets. Following the inspection, major defects in the sewer system will be evaluated and a rehabilitation plan will be developed and scoped for future implementation.