FY 25 Budget Q&A #060: What would the cost to the CIP budget be for the project to ensure that the pump stations to be built as part of waterfront flood mitigation will include publicly accessible bathrooms in the initial design and implementatation?
Page updated on March 28, 2024 at 10:47 AM
XWARNING: You have chosen to translate this page using an automated translation system.
This translation has not been reviewed by the City of Alexandria and may contain errors.
Question: What would the additional cost to the CIP budget be for the project to ensure that the pump station(s) to be built as part of waterfront flood mitigation will include publicly accessible bathrooms in the initial design and implementation? (Councilmember Sarah Bagley)
Response:
The anticipated additional cost for including and delivering finished restrooms within the proposed pump station, as currently conceived, would be approximately $350,000.
The figure below provides the conceptual layout of first-floor restrooms used as a basis for this estimate: