Update: Nov. 24, 2008 |
| > |
Update: Nov. 7, 2008 |
| > |
Update: Oct. 29, 2008 |
| > |
Update: Oct. 16, 2008 |
| > |
Update: Oct. 2, 2008 |
| > |
Update: Sep. 23, 2008 |
| > |
Update: Sep. 9, 2008 |
| > |
Update: Aug. 21, 2008 |
| > |
Update: Aug. 8, 2008 |
| > |
Update: July 25, 2008 |
| > |
Update: July 18, 2008 |
| > |
Update: June 28, 2008 |
| > |
Update: June 21, 2008 |
|
 |
|
|
 |
| Project Manager |
Steve Mason
Special Assistant to City Manager
City of Alexandria
703.838.3861
transloading@alexandriava.gov |
| Other Contacts |
Norfolk Southern
757.629.2713
contactus@nscorp.com |
Hon. John Warner
U.S. Senate
225 Russell Building
Washington, D.C. 20510
202.224.2023
E-mail |
Hon. James Webb
U.S. Senate
144 Russell Building
Washington, DC 20510
202.224.4024
E-mail |
Hon. James Moran
U.S. House of Representatives
2239 Rayburn Building
Washington, DC 20515
202.225.4376
E-mail |
City Council
301 King Street
Alexandria, VA 22314
703.838.4550
E-mail |
|
 |
|
This page contains references and links to all electronic communications among City staff, and between City staff, Norfolk Southern, and the community regarding the establishment and operation of the Ethanol Transloading Facility. The communications, furnished in response to requests made under the Virginia Freedom of Information Act, cover the period from June 20, 2006 at 8 a.m. to May 29, 2008, at 5 p.m.
E-mail addresses and telephone numbers have been redacted to protect the privacy of residents and of City staff whose home and mobile phone numbers were included on the communications. To contact City officials or staff, please use the links on the left side of this page, or Contact Us.
[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Re: PRIORITY--Ethanol facility
Chief, Here's what we have as of our site visit today: 1) The pump system was evaluated and is performing as designed. It will automatically shut off in the event of a ground failure or overflow alarm activation; 2) The grounding system was reported to have been tested initially when installed but there is no supporting paperwork. The grounding system was supposed to be tested again after the asphalt surface was poured but that did not occur. We have requested a ground test ASAP. This will occur on a Saturday when they are not operating and can move all the railcars out of the facility. They will provide us a date for the test; 3) The actual capacity of the containment area is not on site. They have made a few phone calls and we hope to have the actual capacity this afternoon. However, we did a crude field calculation and estimate the holding area to contain approximately 36,475 gallons of fuel. A survey of each rail car show a variable capacity between 30,010 and 30,280 gallons based on make and model of railcar. So if our math is close, the containment area will hold one full railcar load of fuel and a little extra. I will pass on more info as we get it today. Bob
Robert B. Rodriguez Chief Fire Marshal Alexandria Fire Department / Code Enforcement 301 King Street, Room 4200 Alexandria, Virginia 22314 Office (703) 838-4360 Direct (703) 519-3300 ext. 118 Fax (703) 838-3880
-----Adam Thiel/Alex wrote: -----
To: Robert Rodriguez/Alex@Alex From: Adam Thiel/Alex Date: 05/27/2008 10:06AM Subject: Re: PRIORITY--Ethanol facility
Thanks, Bob!
Adam Robert Rodriguez
----- Original Message ----- From: Robert Rodriguez Sent: 05/27/2008 09:56 AM EDT To: Adam Thiel Subject: Re: PRIORITY--Ethanol facility I will send staff out this morning to get the info.
Robert B. Rodriguez Chief Fire Marshal Alexandria Fire Department / Code Enforcement 301 King Street, Room 4200 Alexandria, Virginia 22314
Office xxx-xxx-xxxx Direct xxx-xxx-xxxx ext. 118 Fax xxx-xxx-xxxx
Adam Thiel/Alex
Adam Thiel/Alex 05/27/2008 09:44 AM
| | Bob:
We need the follow-up to occur right now, please...thanks!
Adam ____________________________________ Adam K. Thiel Fire Chief Alexandria Fire Department 900 Second Street Alexandria, VA 22314 Phone: xxx-xxx-xxxx Fax: xxx-xxx-xxxx E-mail: 
Robert Rodriguez/Alex
Robert Rodriguez/Alex 05/27/2008 09:37 AM
| | Chief,
Just to clarify, our instruction was to conduct a survey and identify Fire Prevention issues. As such we did not issue any Notices of Violation. The facility does meet the current requirements of the IFC. Staff requested the following additional items from NS:
- Requested documentation on capacity of secondary containment area;
- Requested grounding details for rail and tanker systems;
- Requested cut sheets and listing information for fuel transfer pump.
Staff is scheduled to follow up with NS next week.
Bob
Robert B. Rodriguez Chief Fire Marshal Alexandria Fire Department / Code Enforcement 301 King Street, Room 4200 Alexandria, Virginia 22314
Office xxx-xxx-xxxx Direct xxx-xxx-xxxx ext. 118 Fax xxx-xxx-xxxx
Adam Thiel/Alex
Adam Thiel/Alex 05/27/2008 09:25 AM
| | Sirs:
Could you please provide (ASAP) an update on NSC's compliance with the FPC at the ethanol trans-loading facility?
My current understanding is that the facility, in its present configuration, complies with all applicable FPC provisions. If there are any outstanding compliance questions, we need to get them answered today so I can brief City Council tonight with the most updated information.
Thanks!
Adam ____________________________________ Adam K. Thiel Fire Chief Alexandria Fire Department 900 Second Street Alexandria, VA 22314 Phone: xxx-xxx-xxxx Fax: xxx-xxx-xxxx E-mail: 
|
|