Update: Nov. 24, 2008 |
| > |
Update: Nov. 7, 2008 |
| > |
Update: Oct. 29, 2008 |
| > |
Update: Oct. 16, 2008 |
| > |
Update: Oct. 2, 2008 |
| > |
Update: Sep. 23, 2008 |
| > |
Update: Sep. 9, 2008 |
| > |
Update: Aug. 21, 2008 |
| > |
Update: Aug. 8, 2008 |
| > |
Update: July 25, 2008 |
| > |
Update: July 18, 2008 |
| > |
Update: June 28, 2008 |
| > |
Update: June 21, 2008 |
|
 |
|
|
 |
| Project Manager |
Steve Mason
Special Assistant to City Manager
City of Alexandria
703.838.3861
transloading@alexandriava.gov |
| Other Contacts |
Norfolk Southern
757.629.2713
contactus@nscorp.com |
Hon. John Warner
U.S. Senate
225 Russell Building
Washington, D.C. 20510
202.224.2023
E-mail |
Hon. James Webb
U.S. Senate
144 Russell Building
Washington, DC 20510
202.224.4024
E-mail |
Hon. James Moran
U.S. House of Representatives
2239 Rayburn Building
Washington, DC 20515
202.225.4376
E-mail |
City Council
301 King Street
Alexandria, VA 22314
703.838.4550
E-mail |
|
 |
|
This page contains references and links to all electronic communications among City staff, and between City staff, Norfolk Southern, and the community regarding the establishment and operation of the Ethanol Transloading Facility. The communications, furnished in response to requests made under the Virginia Freedom of Information Act, cover the period from June 20, 2006 at 8 a.m. to May 29, 2008, at 5 p.m.
E-mail addresses and telephone numbers have been redacted to protect the privacy of residents and of City staff whose home and mobile phone numbers were included on the communications. To contact City officials or staff, please use the links on the left side of this page, or Contact Us.
[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Fw: Ethanol Plan
- To: Adam Thiel
- Subject: Fw: Ethanol Plan
- From: Robert Rodriguez/Alex
- Date: 27 May 2008 16:02:51
- Bcc: Russell Furr/Alex
- Cc: John Catlett
Chief,
Below is the official info on spill
containment from Norfolk Southern which is considerably better than out
rough field calculations. This provides capacity to contain product
from 17 railcars. Today there were 15 railcars on site.
Also, I found my old e-mail which indicated
that the transloading facility went on line April 9.
Bob
Robert B. Rodriguez
Chief Fire Marshal
Alexandria Fire Department / Code Enforcement
301 King Street, Room 4200
Alexandria, Virginia 22314
Office xxx-xxx-xxxx
Direct xxx-xxx-xxxx ext. 118
Fax xxx-xxx-xxxx
----- Forwarded by Robert
Rodriguez/Alex on 05/27/2008 03:47 PM -----
| Russell Furr/Alex
05/27/2008 03:28 PM
|
|
To
| Robert Rodriguez/Alex@Alex
|
|
cc
|
|
|
Subject
| Ethanol Plan |
|
Mr. Rosenthal just called me - he stated
that the official capacity of the containment as engineered when the site
was built is 515,282 gallons, considerably higher than our estimate. He
could not provide the dimensions, but said this came from the engineers
in Atlanta that calculated the design. That was also calculating
the odd shaped areas he said.
Also, he stated that they are trying
to schedule the continuity test within the next two weeks, either this
Saturday or next. He said it might take a few days, he should have
a date by the end of the week.
Russell A. Furr
Assistant Fire Marshal
Code Enforcement Bureau
xxx-xxx-xxxx, ext. 128