 |
| > |
Update: Nov. 24, 2008 |
| > |
Update: Nov. 7, 2008 |
| > |
Update: Oct. 29, 2008 |
| > |
Update: Oct. 16, 2008 |
| > |
Update: Oct. 2, 2008 |
| > |
Update: Sep. 23, 2008 |
| > |
Update: Sep. 9, 2008 |
| > |
Update: Aug. 21, 2008 |
| > |
Update: Aug. 8, 2008 |
| > |
Update: July 25, 2008 |
| > |
Update: July 18, 2008 |
| > |
Update: June 28, 2008 |
| > |
Update: June 21, 2008 |
|
 |
|
|
 |
| Project Manager |
Steve Mason
Special Assistant to City Manager
City of Alexandria
703.838.3861
transloading@alexandriava.gov |
| Other Contacts |
Norfolk Southern
757.629.2713
contactus@nscorp.com |
Hon. John Warner
U.S. Senate
225 Russell Building
Washington, D.C. 20510
202.224.2023
E-mail |
Hon. James Webb
U.S. Senate
144 Russell Building
Washington, DC 20510
202.224.4024
E-mail |
Hon. James Moran
U.S. House of Representatives
2239 Rayburn Building
Washington, DC 20515
202.225.4376
E-mail |
City Council
301 King Street
Alexandria, VA 22314
703.838.4550
E-mail |
|
 |
E-mail Timeline
[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]
Ethonal Project Update
- To: Jannine Pennell
- Subject: Ethonal Project Update
- From: Duane Perry
- Date: 10 Aug 2006 08:23:44
- Bcc:
- Cc: Bob Luckett; William Coates; Maurice Jones; Arthur Dahlberg
Mrs. Pennell,
On Wednesday at 1000 hrs, I and Art
met with a small Army of folks from Nolfork-Southern Railroad to discussed
the proposed Ethanol transfer facility. The meeting started with a brief
program overview of the operations from Nolfork-Southern. Director Dahlberg
started the City's discussion by addressing the possible impact on various
City communities. Items such as noise, environmental problems and fires
hazards were discussed. Director Dahlberg recommended that Nolfork-Southern
conduct community outreach in three phases; phase 1 would be community
notification, phase 2 would be to received concerns from the citizens and
phase 3 would be to address the presented concerns. Also, specific items
were identified and discussed with regards to the security and fire safety.
Those items included the following:
a. Concrete dikes will be constructed
to hold a total of three cars and tanker vehicle. The dike will be designed
for a total capacity of 135, 000 gallons. Tank vehicles would have
access by a ramp system.
b. All spillage will be captured within
the diked area. Spill/drip pans will be used and placed under each connection.
c. The proposed fire hydrant system
was relocated outside the containment area. The proposed location is satisfactory,
however an additional fire hydrant was requested to be installed at the
main entrance. Norfolk Southern was requested to present all plans and
specifications to Supervisor Jones for review and approval.
d. Fire Extinguishers will be placed
100' feet apart with two large wheeled fire extinguishers, 1 at each
end of the diked area.
e. Director Dahlberg also discussed
the possibility of stock piling foam on site to address a possible flammable
liquid fire. The exact amount would be determine once the exact number
rails cars is determined and discussed with our Hazmat Team.
f Security fencing shall be installed
around the entire property. The main gate will be fitted with a large Knox
box containing all necessary information and Knox pad locks will be provided
at all gates.
g. Nolfork-Southern will provide around
the clock security personnel on site.
h. A response and operation plan will
be developed and reviewed with first responders. IN addition, Nolfork-Southern
will provide on-site, hands on training for emergency personnel. (include
Arlington and Fairfax)
i All electrical components sill be
provided or equipped to meet the electrical requirements of NFPA 70. This
standard addresses the concerns over static electricity and the requirements
for bonding and grounding. Nolfork-Southern agreed to all requirements
and will also provide a Scully system. A Scully system will prevent the
transfer of flammable liquid if the ground is not obtained and will stop
the system if the ground is lost.
k. A vapor recovery system will be in
place. All vapors within a tank vehicle will be transferred back into the
rail car and then removed from the site. The entire transfer system will
be an enclosed system. All connections will be provided with "Dry
Fitting" connections. No drips or leaks.
l. Nolfork-Southern will also be obtaining
an annual hazardous use permit. The permit will allow yearly entry and
inspection of the facility.
m. A brief discussion was held on the
possibility of portable master streams. The feasibility will be explored
once they have determine how much water is available and on site.
Once Nolfork-Southern has completed
thier analysis of the site and digested the aboved information a second
meeting will be scheduled.
Duane T. Perry
Deputy Fire Marshal III
Alexandria Fire Department
Code Enforcement Bureau
301 King Street, Room 4200
Alexandria, Virginia 22314
duane.perry@alexandriava.gov
703-519-3300, ext 111
|
|